Airbus is downplaying test results in which an A380 wing undergoing static testing failed slightly before the required design limit.
The wings are supposed to take 1.5 times the design load limit but this one failed at 1.45 times, about 3.3 percent shy of the certification requirement.
Airbus spokeswoman Barbara Kracht said the wing will need some “refinements” but the aircraft is on schedule for certification and first deliveries late this year. “We will need to find out from the data what is really needed but it’s certainly not a redesign of the wing,” Kracht told Associated Press.
In order for an aircraft to be certified here in the U.S., it must withstand the maximum “g” loading specified for that category, plus a 50% overload factor. For example, in the Normal category, the aircraft must withstand a positive load of 3.8g and a negative load of -1.52g at maximum gross weight. It must also be able to withstand an additional 50% of those loads without failing.
These “static” tests, as they’re called, are accomplished on the ground by mechanically loading up the wings. Sometimes this is done by simply placing sandbags on the wings to simulate a load. Large manufacturers like Boeing and Airbus use slightly more expensive methods. I’ve seen video of a 777 wing being tested to failure — the wings bent up to the point where they almost touched. In other words, it handled far more than the required loading.
The requirements for the Transport category are set out in 14 CFR 25.337(b)-(d):
(b) The positive limit maneuvering load factor n for any speed up to Vn may not be less than 2.1+24,000/ (W +10,000) except that n may not be less than 2.5 and need not be greater than 3.8 — where W is the design maximum takeoff weight.
(c) The negative limit maneuvering load factor –
(1) May not be less than −1.0 at speeds up to VC; and
(2) Must vary linearly with speed from the value at VC to zero at VD.
(d) Maneuvering load factors lower than those specified in this section may be used if the airplane has design features that make it impossible to exceed these values in flight.
So if the plane is going to be certified in the Transport category, it will have to handle somewhere between 2.5 and 3.8 positive G — plus 50% — depending on the maximum takeoff weight.
I’ve never heard of an aircraft failing to withstand the 1.5x test. That’s not to say it’s never happened, just that I’m not familar with such an ocurrance.
However you slice it, this has got to be a huge embarrassment for Airbus. Even if the flaw was simply a construction defect in the prototype, it will bring into question every other aspect of the A380’s design and construction in the minds of potential customers, not to mention the flying public.
The wings are supposed to take 1.5 times the design load limit but this one failed at 1.45 times, about 3.3 percent shy of the certification requirement.
Airbus spokeswoman Barbara Kracht said the wing will need some “refinements” but the aircraft is on schedule for certification and first deliveries late this year. “We will need to find out from the data what is really needed but it’s certainly not a redesign of the wing,” Kracht told Associated Press.
In order for an aircraft to be certified here in the U.S., it must withstand the maximum “g” loading specified for that category, plus a 50% overload factor. For example, in the Normal category, the aircraft must withstand a positive load of 3.8g and a negative load of -1.52g at maximum gross weight. It must also be able to withstand an additional 50% of those loads without failing.
These “static” tests, as they’re called, are accomplished on the ground by mechanically loading up the wings. Sometimes this is done by simply placing sandbags on the wings to simulate a load. Large manufacturers like Boeing and Airbus use slightly more expensive methods. I’ve seen video of a 777 wing being tested to failure — the wings bent up to the point where they almost touched. In other words, it handled far more than the required loading.
The requirements for the Transport category are set out in 14 CFR 25.337(b)-(d):
(b) The positive limit maneuvering load factor n for any speed up to Vn may not be less than 2.1+24,000/ (W +10,000) except that n may not be less than 2.5 and need not be greater than 3.8 — where W is the design maximum takeoff weight.
(c) The negative limit maneuvering load factor –
(1) May not be less than −1.0 at speeds up to VC; and
(2) Must vary linearly with speed from the value at VC to zero at VD.
(d) Maneuvering load factors lower than those specified in this section may be used if the airplane has design features that make it impossible to exceed these values in flight.
So if the plane is going to be certified in the Transport category, it will have to handle somewhere between 2.5 and 3.8 positive G — plus 50% — depending on the maximum takeoff weight.
I’ve never heard of an aircraft failing to withstand the 1.5x test. That’s not to say it’s never happened, just that I’m not familar with such an ocurrance.
However you slice it, this has got to be a huge embarrassment for Airbus. Even if the flaw was simply a construction defect in the prototype, it will bring into question every other aspect of the A380’s design and construction in the minds of potential customers, not to mention the flying public.